Analisa Harga Satuan Pekerjaan Persiapan


Diposkan : 31 Mei 2014
Oleh : Endang Kusman

 

No.   URAIAN
SATUAN
VOLUME
HARGA SATUAN
HARGA
     
(Rp)
(Rp)
A-01 1 M' Pagar Sementara Dari Kayu Tinggi 2 m
  - Dolken Kayu Ø 8-10 / 400 cm
Btg
1.2500
28,000.00
35,000.00
  - Semen Portland
Kg
2.5000
1,406.00
3,515.00
  - Pasir beton
M3
0.0050
255,400.00
1,277.00
  - Koral Beton 2/3
M3
0.0090
211,100.00
1,899.90
  - Kayu balok terentang
M3
0.0720
2,640,000.00
190,080.00
  - Paku Biasa 2" - 5"
Kg
0.0600
23,400.00
1,404.00
  - Residu
Kg
0.4000
8,100.00
3,240.00
  - Pekerja
Oh
0.4000
42,000.00
16,800.00
  - Tukang Kayu
Oh
0.2000
65,000.00
13,000.00
  - Kepala Tukang
Oh
0.0200
75,000.00
1,500.00
  - Mandor
Oh
0.0200
80,000.00
1,600.00
    Jumlah
269,315.90
  Dibulatkan
269,316.00
A-02 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m
  - Dolken Kayu Ø 8-10 / 400 cm
Btg
1.2500
28,000.00
35,000.00
  - Semen Portland
Kg
2.5000
1,406.00
3,515.00
  - Seng Gelombang BJLS-30
Lbr
1.2000
62,900.00
75,480.00
  - Pasir beton
M3
0.0050
255,400.00
1,277.00
  - Koral Beton 2/3
M3
0.0090
211,100.00
1,899.90
  - Kayu balok terentang
M3
0.0720
2,640,000.00
190,080.00
  - Paku Biasa 2" - 5"
Kg
0.0600
23,400.00
1,404.00
  - Meni Besi
Kg
0.4500
30,400.00
13,680.00
  - Pekerja
Oh
0.4000
42,000.00
16,800.00
  - Tukang Kayu
Oh
0.2000
65,000.00
13,000.00
  - Kepala Tukang
Oh
0.0200
75,000.00
1,500.00
  - Mandor
Oh
0.0200
80,000.00
1,600.00
    Jumlah
355,235.90
  Dibulatkan
355,236.00
A-03 1 M' Pagar SementaraKawat Duri Tinggi 1,80 m
  - Dolken Kayu Ø 8-10 / 400 cm
Btg
1.0000
28,000.00
28,000.00
  - Semen Portland
Kg
2.0000
1,406.00
2,812.00
  - Kawat Duri
Kg
2.5000
63,500.00
158,750.00
  - Pasir beton
M3
0.0050
255,400.00
1,277.00
  - Koral Beton 2/3
M3
0.0090
211,100.00
1,899.90
  - Paku Biasa 2" - 5"
Kg
0.0600
23,400.00
1,404.00
  - Pekerja
Oh
0.3000
42,000.00
12,600.00
  - Tukang Kayu
Oh
0.2000
65,000.00
13,000.00
  - Kepala Tukang
Oh
0.0200
75,000.00
1,500.00
  - Mandor
Oh
0.0200
80,000.00
1,600.00
    Jumlah
222,842.90
  Dibulatkan
222,843.00
A-04 1 M2 Pengukuran Dan Pasang Bouwplank
  - Kayu kaso 5/7
M3
0.0120
1,870,500.00
22,446.00
  - Paku Biasa 2" - 5"
Kg
0.0200
23,400.00
468.00
  - Kayu papan albasia
M3
0.0070
2,071,700.00
14,501.90
  - Pekerja
Oh
0.1000
42,000.00
4,200.00
  - Tukang Kayu
Oh
0.1000
65,000.00
6,500.00
  - Kepala Tukang
Oh
0.0100
75,000.00
750.00
  - Mandor
Oh
0.0050
80,000.00
400.00
    Jumlah
49,265.90
  Dibulatkan
49,266.00
A-05 1 M2 Pembuatan Kantor Sementara dgn Lantai Diplester
  - Dolken Kayu Ø 8-10 / 400 cm
Btg
1.2500
28,000.00
35,000.00
  - Kayu Balok terentang
M3
0.1800
2,640,000.00
475,200.00
  - Paku Biasa
Kg
0.8500
23,400.00
19,890.00
  - Besi Strip
Kg
1.1000
26,800.00
29,480.00
  - Semen Portland
Kg
35.0000
1,406.00
49,210.00
  - Pasir Pasang
M3
0.1500
233,400.00
35,010.00
  - Pasir beton
M3
0.1000
255,400.00
25,540.00
  - Koral Beton2/3
M3
0.1500
211,100.00
31,665.00
  - Bata Merah
Bh
30.0000
775.00
23,250.00
  - Seng Plat
m'
0.2500
15,815.00
3,953.75
  - Kawat harmonika
M2
2.0000
35,900.00
71,800.00
  - Kaca Polos 3mm
M2
0.0800
87,400.00
6,992.00
  - Kunci Tanam
Bh
0.1500
94,500.00
14,175.00
  - Plywood 120 x 240 x 0,4 cm
Lbr
0.0600
140,000.00
8,400.00
  - Pekerja
Oh
2.0000
42,000.00
84,000.00
  - Tukang Kayu
Oh
2.0000
65,000.00
130,000.00
  - Tukang Batu
Oh
1.0000
65,000.00
65,000.00
  - Kepala Tukang
Oh
0.3000
75,000.00
22,500.00
  - Mandor
Oh
0.0500
80,000.00
4,000.00
    Jumlah
1,135,065.75
  Dibulatkan
1,135,066.00
A-06 1 M2 Pembuatan Gudang Semen dan Alat-alat
  - Dolken Kayu Ø 8-10 / 400 cm
Btg
1.7000
28,000.00
47,600.00
  - Kayu balok terentang
M3
0.2100
2,640,000.00
554,400.00
  - Paku Biasa
Kg
0.3000
23,400.00
7,020.00
  - Semen Portland
Kg
10.5000
1,406.00
14,763.00
  - Pasir Beton
M3
0.0300
255,400.00
7,662.00
  - Koral Beton 2/3
M3
0.0500
211,100.00
10,555.00
  - Seng Gelombang BJLS 30
Lbr
1.5000
62,900.00
94,350.00
  - Pekerja
Oh
1.0000
42,000.00
42,000.00
  - Tukang Kayu
Oh
2.0000
65,000.00
130,000.00
  - Kepala Tukang
Oh
0.2000
75,000.00
15,000.00
  - Mandor
Oh
0.0500
80,000.00
4,000.00
    Jumlah
927,350.00
  Dibulatkan
927,350.00
A-07 1 M2 Pembuatan Bedeng Buruh
  - Dolken Kayu Ø 8-10 / 400 cm
Btg
1.2500
28,000.00
35,000.00
  - Kayu balok terentang
M3
0.1860
2,640,000.00
491,040.00
  - Paku Biasa
Kg
0.3000
23,400.00
7,020.00
  - Semen Portland
Kg
18.0000
1,406.00
25,308.00
  - Pasir Beton
M3
0.0300
255,400.00
7,662.00
  - Koral Beton 2/3
M3
0.0500
211,100.00
10,555.00
  - Seng Gelombang BJLS 30
Lbr
1.5000
62,900.00
94,350.00
  - Pekerja
Oh
1.0000
42,000.00
42,000.00
  - Tukang Kayu
Oh
2.0000
65,000.00
130,000.00
  - Kepala Tukang
Oh
0.2000
75,000.00
15,000.00
  - Mandor
Oh
0.0500
80,000.00
4,000.00
    Jumlah
861,935.00
  Dibulatkan
861,935.00
A-08 1 M2 Membersihkan Lapangan dan Perataan
  - Pekerja
Oh
0.1000
42,000.00
4,200.00
  - Mandor
Oh
0.0500
80,000.00
4,000.00
    Jumlah
8,200.00
  Dibulatkan
8,200.00
A-09 1M2 Pembuatan Jalan Sementara
  - Batu Belah 15/20
M3
0.1500
205,500.00
30,825.00
  - Batu Pecah 5/7
M3
0.0900
196,000.00
17,640.00
  - Pasir Pasang
M3
0.0100
233,400.00
2,334.00
  - Pekerja
Oh
1.0000
42,000.00
42,000.00
  - Mandor
Oh
0.0500
80,000.00
4,000.00
    Jumlah
96,799.00
  Dibulatkan
96,799.00
A-10 1 M3 Bongkaran Beton Bertulang
  - Pekerja
Oh
6.6670
42,000.00
280,014.00
  - Mandor
Oh
0.3330
80,000.00
26,640.00
    Jumlah
306,654.00
  Dibulatkan  
306,654.00
A-11 1 M3 Bongkaran Dinding Tembok Bata Merah
  - Pekerja
Oh
6.6670
42,000.00
280,014.00
  - Mandor
Oh
0.0330
80,000.00
2,640.00
    Jumlah
282,654.00
  Dibulatkan
282,654.00
A-12 1 M¹ Pagar beton Pracetak ( 5 x 50 x 213 ) cm
  - Panel Beton Pracetak
Lbr
0.9860
199,200.00
196,411.20
  - Kolom Beton Pracetak
Btg
0.5250
264,000.00
138,600.00
  - Pasir Beton
M3
0.0740
255,400.00
18,899.60
  - Koral 2/3
M3
0.1460
211,100.00
30,820.60
  - Semen abu - abu
Kg
45.0000
1,406.00
63,270.00
  - Pekerja
Oh
0.3750
42,000.00
15,750.00
  - Tukang Batu
Oh
0.1250
65,000.00
8,125.00
  - Kepala Tukang
Oh
0.0120
75,000.00
900.00
  - Mandor
Oh
0.0190
80,000.00
1,520.00
    Jumlah
474,296.40
  Dibulatkan
474,296.00
A-13 1 M¹ Pagar kawat ayam tiang besi L50.50.5, tinggi 1 m'
  - Kawat ram ayam
Lbr
0.4340
14,900.00
6,466.60
  - Besi siku L 50.50.5
Kg
6.7860
18,300.00
124,183.80
  - Besi pelat (1,2 x 3) mm
Kg
0.0424
18,300.00
775.92
  - Baut
bh
4.0000
600.00
2,400.00
  - Semen Portland
Kg
2.5000
1,406.00
3,515.00
  - Pasir beton
M3
0.0050
255,400.00
1,277.00
  - Koral Beton 2/3
M3
0.0090
211,100.00
1,899.90
  - Pekerja
Oh
0.3750
42,000.00
15,750.00
  - Tukang Batu
Oh
0.1250
65,000.00
8,125.00
  - Kepala Tukang
Oh
0.0120
75,000.00
900.00
  - Mandor
Oh
0.0190
80,000.00
1,520.00
    Jumlah
166,813.22
  Dibulatkan
166,813.00
A-14 1 M2 Pagar BRC lengkap dengan tiang
  - BRC lengkap dengan tiang
Lbr
0.4340
171,300.00
74,344.20
  - Semen Portland
Kg
2.0000
1,406.00
2,812.00
  - Kawat Duri
Kg
2.5000
63,500.00
158,750.00
  - Pasir beton
M3
0.0050
255,400.00
1,277.00
  - Koral Beton 2/3
M3
0.0090
211,100.00
1,899.90
  - Pekerja
Oh
0.3750
42,000.00
15,750.00
  - Tukang Batu
Oh
0.1250
65,000.00
8,125.00
  - Kepala Tukang
Oh
0.0120
75,000.00
900.00
  - Mandor
Oh
0.0190
80,000.00
1,520.00
    Jumlah
265,378.10
  Dibulatkan
265,378.00
A-15 1 M2 Steiger Werk / perancah dari Bambu
  - Bambu Ø 6 - 10 (600) cm
btng
1.0000
25,000.00
25,000.00
  - Tali ijuk
kg
0.2500
23,400.00
5,850.00
  - Pekerja
org
0.2500
42,000.00
10,500.00
  - Tukang kayu
org
0.0170
65,000.00
1,105.00
  - Kepala tukang
org
0.0020
75,000.00
150.00
  - Mandor
org
0.0130
80,000.00
1,040.00
    Jumlah
43,645.00
  Dibulatkan
43,645.00
A-16 1 M' Cerucuk Bambu
  - Bambu Ø 7 -10 (400) cm
btng
1.2500
25,000.00
31,250.00
  - Pekerja
org
0.5000
42,000.00
21,000.00
  - Mandor
org
0.0250
80,000.00
2,000.00
    Jumlah
54,250.00
  Dibulatkan
54,250.00